Restoration of signal (Nov 2014)

The signal post has now been sand blasted and primed. It was then loaded on a flat bed truck ready for transport from Alresford to S&T Cover at Eastleigh.

Loading signal on flatbed

Loading signal on flatbed

The signal parts were also transported,

Signal parts primed and ready for shipment to S & T Cover. Some of these parts were supplied by the Kent & East Sussex Railway

Signal parts primed and ready for shipment to S & T Cover. Some of these parts were supplied by the Kent & East Sussex Railway

Arrival at S&T Cover

Arrival at S&T Cover

The process of procuring the missing parts and assembly now starts.