Further path work on the Hayling Billy Trail (7 July 2014)

Following our Partnership (Hampshire County Council, Havant Borough Council and Hayling’s Best (HB50) meeting, further path work has been agreed. Summary below:

Having completed the 250m long rebuild of the north end of the Trail (see path improvement ), the granular material for which is presently behaving as expected, we have been able to commission a further length of rebuilding. This will be from the west end of the section recently rebuilt, southwards down the trail along the railway route, towards the Oysterbeds north access, along a length that whilst firm underfoot is poorly drained and has a poor surface which traps water in wet weather. Funding for this section is from the Heritage Lottery Fund (HLF). 

 The construction will be different from that used on the initial 250m section, since the railway solum is wider. We plan to excavate a 2m wide shallow trench (100mm or so deep) down the west side of the Trail and use this shallow trench for the construction of the new path. In this way we hope to avoid the use of edging timbers and so as a result be able to rebuild a longer section of path using the money ‘saved’. The untouched east side of the path will remain suitable for equestrians and it is planned to erect small notices suggesting pedestrians and cyclists use the west side and equestrians the east side. This all hinges on how well we can excavate the shallow trench for the new material, and also achieving correct drainage which may require some work to the east side. We’re taking levels today just to confirm matters, but I thought you would appreciate a ‘heads up’ regarding this extra work which will require, as before, a 3 week closure of the Trail. In this way we should be clear by the school holiday.

Excess material coming off the Trail from the excavation of the west side, will be used to supplement shoreline defences alongside the Trail in this location. You may have seen we have already been doing this at the north end of the Trail, using surplus materials from the ‘main job’.


This work is scheduled to commence 7 July 2014.

 